On a private commercial job in Texas, a subcontractor or supplier must send a notice of claim by the 15th day of the third month after each month of unpaid work. Work in January: notice by April 15.

The rule since 2022

H.B. 2237 rewrote Texas lien notices. It applies when the original contract, between the owner and the general contractor, was entered into on or after January 1, 2022; older original contracts follow the earlier law. Every claimant other than the general contractor now sends the same notice, to the owner and to the general contractor, under Tex. Prop. Code §53.056(a-1). The old second-month notice for lower tiers is gone. On residential projects the deadline is the 15th day of the second month instead.

One notice covers one month of work. If you are unpaid for three months, each month has its own deadline.

2026 notice deadlines, commercial projects

Month of workStatute's countIf that is a weekend or holiday, act by
January 2026Wednesday, April 15, 2026Same day
February 2026Friday, May 15, 2026Same day
March 2026Monday, June 15, 2026Same day
April 2026Wednesday, July 15, 2026Same day
May 2026Saturday, August 15, 2026Friday, August 14, 2026
June 2026Tuesday, September 15, 2026Same day
July 2026Thursday, October 15, 2026Same day
August 2026Sunday, November 15, 2026Friday, November 13, 2026
September 2026Tuesday, December 15, 2026Same day
October 2026Friday, January 15, 2027Same day
November 2026Monday, February 15, 2027Friday, February 12, 2027
December 2026Monday, March 15, 2027Same day

When the 15th falls on a Saturday, Sunday or legal holiday, §53.003(e) extends it to the next business day. We show the business day before, so you never rely on the extension.